Saturday, May 18, 2013

Drywall & Siding

This week saw a good bit of progress - the fireplace was installed, the exterior siding and deck platform completed, and the drywall is now up. One more coat of spackle and sanding and they'll be moving on to the flooring.














Sunday, May 5, 2013

Inspections

Not much visible progress the last week - the electric, plumbing and framing inspections were all cleared last week.  Since we decided to replace the dining room and living room floors to match the great room, I decided to put in some sweat equity this weekend and start ripping up the old floors. We have two layers to remove - the cherry floating floor ( which is easy to remove) and the original oak underneath (not so easy).
Expecting to have the insulation and drywall going in later this week.